Pattern Energy must leave Molokai

| July 15, 2011 | 0 Comments
Pattern Energy must leave Molokai

I Aloha Moloka’i News Release The proposed $3-5 billion “Big Wind” project to build 90 huge wind turbines on Molokai and a billion-dollar undersea cable has come to a crashing halt. Now that the Public Utilities Commission has ordered Hawaiian Electric (HECO) yesterday to stop this mega-project and restart it with new bidders, I Aloha […]

Continue Reading

PUC requires HECO to reopen renewable energy bids

| July 15, 2011 | 0 Comments
PUC requires HECO to reopen renewable energy bids

Public Utilities Commission News Release HONOLULU – In a July 14, 2011 Decision and Order, the Public Utilities Commission (PUC) required Hawaiian Electric Company (HECO) to restart within 90 days the bidding process for renewable energy generation that would have come from a 200 MW Molokai wind project. The decision also allows the Castle & […]

Continue Reading